|

Looking
west on J Ave with the plant in the background on the left. The row of
soldier beams are the top eight feet of 40 ft long reinforcing beams
encased in 36” diameter caissons below grade. They are part of the
excavation retention system for the new Chlorine Contact
Tank/Reservoir/Pump Station excavation. The structure will be roughly
300 feet long, 90 feet wide and 34 feet deep.


Trailer loaded with six high voltage switches, which will allow for
sectionalizing the new 12,470-volt electrical feed “loop” that will
surround the J Ave Plant. This will enable the operators to feed power
from either direction to isolate an electrical fault at any point in the
loop while maintaining power service to the rest of the system.

An underground high-voltage electrical vault just after it was set in
place. This is also an integral part of the electrical loop at the J
Ave. Plant. The circular openings in the walls are for conduits
carrying the power conductors to various locations, some of which are
shown in photo #16 before they were encased in reinforced concrete.



The
final stages of making up a 42 inch diameter ductile iron pipe joint
with a retaining gland to prevent the joint from separating under
pressure. This particular pipe line carries storm drainage to the Storm
Water Detention Basin, for which the beginnings of foundation
construction are shown in picture #10. This Basin will provide on-site
storage for excess storm water until it can be slowly pumped into storm
sewers after surface flow has decreased, helping to reduce peak flow in
storm drainage systems.



A
rooftop view of the CCT/Reservoir/Pump Station construction area looking
eastward


A
30” dia. gate valve and 36” dia. stainless steel “hot tap” sleeve, which
were installed on the existing 36” Prairie Valley water supply main
while it remained in service. This was necessary to maintain plant
delivery capacity due to ice damage to the Penn Ave supply main under
the Cedar River last winter.

 |